Fabrication of 2 bundles
August 2020
Value: $165,000
The following scope of work was carried out:
-
Supply material per chemical composition on drawing 00-104/1
-
Fabrication of 2 bundles (LPG and Steam)
-
Supply and fabrication of baffles, tie rods and 2 end flanges (460NR Boiler Plate)
-
NDT (100% UT and 100% MPI for Nozzle Welds)
-
NDT (Spot - 10% Radiographic for Bundle welds)
-
PWHT LPG Bundle to 620 deg C for 1 hour (Note 1)
-
Hardness Tests (100% Per requirements of 00-104/1 210VHN (200BHN))
-
Hydrotesting LPG bundle to 4,500 kPa(g) and Steam bundle to 1,883 kPa(g)
-
Drying out bundles prior to delivery
-
Painting external surface end flanges and nozzles to an equivalent international paint spec from Dulux Durepon P14
-
MDR and QA Documentation (ITP, WPS, Welders Qualifications)
-
Delivery to Site (Caltex Refinery - Lytton)